​​​​Project Update as of September 10, 2025

Westview Ta na wa Ns7éyxnitm tlá Teltíwet Elementary is growing! Check out this incredible timelapse of the prefabricated modular addition under construction at Westview. This video covers just 13 working days from August 12 when the concrete slab was poured, to August 27 when the bulk of the installation was completed. Watch this space for updates as the project nears completion.​

The new addition to Westview Elementary supports a healthy and vibrant learning community. We are excited by the innovative approach to building that will add more space and modern classrooms to better meet students’ needs.​​

 

​Project Update as of August 18, 2025

WestviewElementary20250818_1.jpg
WestviewElementary20250818.jpg

​Construction of the 4 classroom addition to Westview Elementary is progressing smoothly and on schedule. The superstructure erection is well underway, with several key milestones reached:

  • Center columns erected
  • First floor wall panels erected
  • Second level glu-lam floor beams placed
  • Second level CLT floor panels placed
  • Second level wall panels erected​

Stay tuned for more updates as the project continues to take shape!​

Project Update as of July 14, 2025

Westview Elementary.jpg
Construction of the 4 classroom addition to Westview Elementary is well underway. The project is unique due to the fact that the building superstructure will be pre-fabricated off-site. This process will significantly shorten the duration of construction.

A local North Vancouver contractor, Halse-Martin Construction Co. Ltd., has been retained as the General Contractor, responsible for overall construction of the addition. BC Passive House has been retained to pre-fabricate the superstructure in their Pemberton facility. 

Upon completion of the concrete slab main floor, in late July, the pre-fabricated superstructure components will be delivered to site on a daily basis and erected by crane over a 3 week period, currently this is scheduled from August 5 to August 22.

Following the erection of the superstructure, exterior and interior finishing will be completed during the following few months. Work is currently scheduled to be complete prior to the end of 2025.

Westview Elementary site sign.pdf

​​Westview Elementary Project Update - February 6, 2025.pdf

​Funding Announcement - June 16, 2024

Read the full Ministry Release on our News & Announcements.

Families in North Vancouver will have 100 more student spaces, part of government’s plan to expand schools faster.

“As we welcome more students to fast-growing communities like North Vancouver, we are finding better solutions to deliver more classrooms as quickly as possible,” said Rachna Singh, Minister of Education and Child Care. “This new expansion will serve students for decades to come.”

A new four-classroom prefabricated addition is coming to Westview Elementary school. The use of prefabricated materials means students will have modern learning environments, which include multiple classrooms that can be connected by corridors. The new classrooms are expected to be ready for students by fall 2025. With sustainable and energy-efficient designs, the additions also align with the Province’s CleanBC targets and meet B.C.’s enhanced energy requirements.  >> Read more.​